Hyperscaler Greenfield Data Centre
CLIENT
Confidential
SERVICES
Project Management; Construction Management
Project Description & Our Role
The project involves a 6-storey, 60MW greenfield data centre.
AIS-Hill provided a team of project managers and safety professionals to support the client in delivering the first two phases of this 60MW data centre project.
Appointed in Q1 2022, while the superstructure was nearing completion and MEP works were still in progress, our PM team was instrumental in helping the project overcome various delays and setbacks to achieve Power Turn-on and TOP in accordance with the project schedule.